Construction Update # 1 - August 8, 2019
Campus is transforming before our eyes as construction continues to move swiftly! To learn more about upcoming plans and how you can get involved, check out the Transformations Campaign website.
Academic Building - construction began May 2019
May 6, 2019 asphalt removal began in the northeast corner of the parking lot to make way for the new academic building.
Ground was prepped and concrete foundation installed.
Exterior walls were then constructed on the foundation.
The first of the exterior walls were lifted into place.
View of exterior walls of academic building from the 7th floor of our current building.
View of new academic building in progress from 18th and Tauromee.
Parking Garage - completed August 2019
Demolition of the International Center to make room for new parking garage.
Lower level of parking garage being prepared.
Concrete poured on second level of parking garage.
Completed garage, lower level entrance
Completed garage, upper level entrance
View from upper level looking back at Donnelly's main tower
Check back often for more updates!